Unfinalize line to cancel on PO is resulting in budget error ref'd doc has been finalized
PS FSCM PUM 47, PT 8.59
I have a client who attempted to unfinalize a line on the PO to resource to a different PO. Steps followed:
Go to PO schedule, line to be unfinalized
Unfinalize line
Budget check
Save PO
Cancel line
Budget Check — get error that Ref'd doc has been finalized
Requisition will allow line to be sourced to a new PO — neither PO will budget check successfully.
Any ideas?
Kari