Scenario:
The user reports that a Wave is still marked as “In Progress”, even though the corresponding order has already been shipped and billed.
Solution:
The most common reason a Wave remains "In Progress" is that there are associated pick tasks that are still in progress. This is a key dependency in the WMS (Warehouse Management System) process.
In many cases, this issue occurs because the Item Fulfillment was manually created through the NetSuite UI rather than processed through the WMS which cause the Pick Task to not be linked in the Item Fulfillment.
If it is necessary to reflect the correct status and clean up the Wave:
- Delete the existing Item Fulfillment that was manually created.
- Identify the Pick Tasks tied to the wave. Reverse any pick tasks that are still open or partially completed.
- Redo the picking process using WMS properly so that:
- The Pick Tasks are correctly executed and marked as Done.
- Once all Pick Tasks are complete, the Wave will automatically update its status to Done.
-----
If you find this information useful, let us know by reacting or commenting on this post!