Hello Team,
I have EOS Checklist, which as below an example:

(Group A)
Task 01
Task 02

(Group B)
Task 03
Task 04


i already defined the 4 tasks in one single template, but i have a requirement that Group B tasks start/triggered only after the 2 tasks of Group A are completed
are preceding task field can be used to achieve this? or any workaround?

Thanks