Register today for Oracle CloudWorld. October 17th - 20th, Las Vegas

Register now

Hillel Cooperman, Senior VP of User Experience Design, has a message for you on Oracle CloudWorld

Watch now
How to create job set to run Demand Management (DM) Plan followed by Supply Plan (SP) — Cloud Customer Connect
You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register

How to create job set to run Demand Management (DM) Plan followed by Supply Plan (SP)

Received Response
26
Views
2
Comments
edited Dec 7, 2020 10:29AM in Supply Chain Planning and Collaboration 2 comments

Summary

Instead of scheduling jobs to trigger plan run, I want to create job set to run Demand Management (DM) Plan followed by Supply Plan (SP).

Content

Currently, I have scheduled plan run at a fixed time.

But now I want to create job set to reduce the idle/buffer time between 2 plan run.

This will give planner more time to analysis plan output.

I need a document/guidance on how to create a job set to run Demand Management (DM) Plan followed by Supply Plan (SP).

Initial Steps identified:

1. Navigate to Setup and Maintenance

2. Under Setup: Supply Chain Planning

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!