How to create job set to run Demand Management (DM) Plan followed by Supply Plan (SP)

edited Dec 7, 2020 10:29AM in Supply Chain Planning and Collaboration 2 comments

Summary

Instead of scheduling jobs to trigger plan run, I want to create job set to run Demand Management (DM) Plan followed by Supply Plan (SP).

Content

Currently, I have scheduled plan run at a fixed time.

But now I want to create job set to reduce the idle/buffer time between 2 plan run.

This will give planner more time to analysis plan output.

I need a document/guidance on how to create a job set to run Demand Management (DM) Plan followed by Supply Plan (SP).

Initial Steps identified:

1. Navigate to Setup and Maintenance

2. Under Setup: Supply Chain Planning