Best approach to work with team activities for multiple days?
Summary:
The client wants to create activities for multiple days and also change frequently the resources assigned.
Content (required):
Hello Community,
Does anybody know some way to work long activities(multiple days duration) and assign multiple resources? Description of the desired scenario below:
For example create a installation activity that has a duration of 1 week, the first two days requires 5 Technicians(with Work Skill A) but for the next 3 days need 2 additional Technicians(with Work Skill B).
Thanks and regards!
Version (include the version you are using, if applicable):
22A
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged:
1