Maintenance Work Order in Preventative Maintenance Use Case

Summary:

MWO created from maintenance program and MWO created from Service Charges Posting

Content (required):

In Preventative Maintenance Use Case, MWO is created from maintenance program/forecast. Then SR and Service WO are created, once charges are posted for Service WO, a MWO is also created for cost record. My question is - do we use the same MWO (created from PM program) for Service Charges posting?

Thanks,

Adam

Version (include the version you are using, if applicable):

22B

Code Snippet (add any code snippets that support your topic, if applicable):