Autorouting % and Rescheduling
Summary:
Content (required):
Hi All,
On the routing tab one of the tiles is Autorouting %. We want to know if rescheduling an activity in OFS counts as a manual move and lowers the %.
Two rescheduling methods:
- Using the Move Tool / Assignment Assistant to change the date on the activity. No resource change, just the date.
- Using the standard action reschedule_activity.
Thanks!
Version (include the version you are using, if applicable):
22D
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged:
0