You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register

Fusion: PR not created from the planned order where BPA validation fails.

edited Aug 13, 2024 4:06PM in Self Service Procurement 6 comments

PR not created from the planned order where BPA validation fails. Is there a way to bypass this and achieve the requirement? If the BPA is not valid then PR should be created based on the item master's price list.

Planned order is released from the Supply plan. Planned order number: 13381198

Planned order created for 4600 qty, and item’s price is Rs. 744.61 defined in the BPA.
=4600 * 744.61
=34,25,206
In the BPA, remaining amount left is 17,53,690
Due to which the planned order is not getting converted to the PR/PO. It throws error in the supply orchestration. Here Planned order is validating with the BPA.

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!