Oracle Journeys – Dependent Task Not Retriggered After Reopening and Recompleting Previous Task
We are currently facing a limitation/question regarding task dependencies in Oracle Journeys.
Scenario
We have the following setup in a Journey:
- Task A → completed by the user
- Completion of Task A automatically triggers Task B
- Task B is intended to validate or process the information entered in Task A
This works correctly during the initial execution.
Issue Encountered
After Task A was completed and Task B was triggered, the validator/reviewer noticed that some information entered in Task A needed to be corrected.
To handle this:
- We sent a notification to the user requesting updates
- We reopened Task A
0