Operation and WO completion dates are not auto updated based on resource duration in Redwood

Summary:

Operation and WO completion dates are not auto updated based on resource duration in Redwood

Content (please ensure you mask any confidential information):

  1. Create a WO from Maintenance Supervision
  2. Add an operation
  3. Add a resource with a duration of 15min
  4. Notice that operation or work order dates remain same irrespective of the resource duration

Resource's UOM belongs to the same class as defined in the profile 'RCS_DEFAULT_UOM_CLASS_CODE_FOR_SVC_DURATION'. Scheduling method is 'Default scheduling' and 'Firm' is unchecked.

Version (include the version you are using, if applicable):

26B


Code Snippet (add any code snippets that support your topic, if applicable):