Best Of
Re: Patch Planning for OEM Database (19.15) and OMS
Hello @User_YCQFH,
As can be seen from the following MOS note, a minimum of 19c RU11 with overlay patch is needed for OEM repository DB for OEM 13.5 Ru26.
13.5.0 Enterprise Manager Cloud Control Base Platform Monthly Release Update (RU) 26 (Doc ID 3083929.1)
Regards,
Satya
Re: In WSJ, UBE start time shows the same as UBE end time
It'd be nice when insert to F986110 (The 3rd SQL in the log), use the actual end time to populate the Time Activity column, as system already has this info when updating to F986114 (The 2nd SQL in the log).
Re: In WSJ, UBE start time shows the same as UBE end time
Thanks David, the doc you attached here exactly answers my inquiry. In my case, the parent UBE calls the child UBE in async mode.
Re: Q: R12.4 we launch ASCP plan in Monday why get forecast in past 1 week ?
Hi @user11983346 ,
Please set the organization parameter Include Past Due Forecast to 0 to avoid past due forecasts.
Nav: Advanced Supply Chain Planner ® → Setup → Parameters.
Ensure that the above is set up for plan owning organization as well.
Best Regards,
Mohan Balaji
Re: Why do Actual Labor Units Reset to Zero When Scheduling?
I have the same issue today that my Actual units are resetting to 0 when I schedule a project.
We utilize manual Actual hours updates each week that alighn with actual field used timesheets, and when I schedule the project my hours are disappearing just like the original poster pointed out. This Bug is still alive in my opinion.
Re: Why Total Forecast is Different?
Hi @Aji NS ,
You can plan at any aggregation level as per your business need.
However, the specific scenario of forecast disaggregation doesn't work.
You can load your forecasts using 4\4\5 or 5\4\4 calendars and use the same calendar as org manufacturing calendar. In which case, you can enter the forecasts and run plans as per bucketing needs of your business.
Hope the above helps!
Best Regards,
Mohan Balaji
NOTE: In the best interest of community, Please accept the answer and conclude the thread if the query is addressed.
Re: Can ASCP Plan without Forecast?
Hi @Aji NS ,
Yes, you can run ASCP plans with sales orders alone or MDS or MPS or Work orders\supply schedules depending on your business need.
Hope the above helps!
Best Regards,
Mohan Balaji
Re: vdsm is missing cpu model flags
Hi There
Assuming you finished the upgrade correctly, Please have a look at this KM: OLVM: Host Non-Operational with the Message: CPU_TYPE_UNSUPPORTED_IN_THIS_CLUSTER_VERSION (Doc ID 3056480.1)
You would need to downgrade the edk2-ovmf package to version edk2-ovmf-20240227-5.el8.noarch
You might need to specify the exact rpm version when doing #dnf downgrade <package>
Thanks
Nash Oudha
Re: Edit WBS while in a Program
Hi @RonVongs-Oracle what is in the knowledge document is exactly what I mean. I am not able to find the idea in the OPC Idea section, do you have a link so I can give it an upvote?