Re: please share the white paper document for oracle project management implementation steps
Hi @User_7KDDZ,
Thanks. Please refer to this link: https://docs.oracle.com/cd/E26401_01/doc.122/e49019.pdf
For more information you can follow below steps.
The Oracle Projects Implementation Guide (and other documentation) is available on Oracle Help Center.
1. Enter the following url into your browser's address window: http://docs.oracle.com
2. Select the "Applications" icon and then the "E-Business" tab
3. Select the link appropriate to your E-Business Suite release
4. Click on the Tab "Projects"".
5. On the right hand side of the page, under the Projects section, the documents are listed
6. On the line for the Oracle Projects Implementation Guide, select either HTML or PDF link.
Regards,
Piyush
Re: New Tax Rate Effective 2026, Patch 38630519: 2026 U.S. FEDERAL WITHHOLDING TAX CHANGES
It was SR 4-0001593464.
General question
With the recent changes, I'm not able to navigate as before to access all PUMs (images) released, download, see scheduled date(s) for next release etc, etc. Right now I'm able to access only the Community Support. Anyone can help show how to access the other support where we used also to create tickets for the issues?Thank you.
Armand
ArmandV
Question on Setup and Billing/Revenue for Grant with Changing Pre-Paid Amounts and Events
I am looking for some advice on how best to handle a pre-paid grant/contract where the pre-paid amounts and events are not known at the time of grant setup. Thus, the grant/contract have been set up as a typical cost-reimbursable grant/contract.
My understanding from the client is that the grant sponsor contacts them throughout the grant and asks them to submit a billing for costs that have not yet occurred if there is a chance the grant sponsor would not able to pay promptly if they waited until the costs had occurred and the client submitted the billing after the fact (for example the possibility of a government shutdown). However, most of the costs for the grant are still billed to the sponsor after occurring.
For example, the grant may look something like this:
Start and end dates: 7/1/2024 - 6/30/2026
Grant is a traditional cost-reimbursable with billing actual costs after the fact through 12/31/2024. Then the grant sponsor may ask the client to bill $10,000 on 1/1/2025 for a specific grant component where costs have not yet occurred but are anticipated. The rest of the grant is anticipated to be billed after the fact. Fast forward to Sept 2025, and the sponsor may again ask the client to bill $10,000 for anticipated costs that have not yet occurred. This $10,000 payment may only be for a specific part of the grant - perhaps a specific subcontract - and would not be applied to costs for other parts of the grant even during the Sept/Oct time frame. Those other costs would still be billed after the fact.
Ideally, how would a grant like this be set up and managed so that revenue is correct?
Also, does anyone have any suggestions on how best to manage this given that the grant and contract have already been set up as a traditional cost reimbursable without a pre-paid contract line?
Thanks!
Re: Question on Setup and Billing/Revenue for Grant with Changing Pre-Paid Amounts and Events
Hi Michele,
The scenario you describe can be handled in the system (Contracts). Crucial point here is that either cost-reimbursement or pre-paid, they both have the same pricing method which is, 'as incurred'.
If sponsor pays upfront some funding and then requires billing (invoices) for subsequent payments, you can set up the contract as cost-reimbursement with contract limit same as the contract value and then enter one prepaid event for the amount they will pay w/o cost-incurred).
When expenses are hitting the ledger/project costing then at the beginning you run utilization to exhaust the pre-paid value. When the prepaid is depleted, system will generate a debit invoice which can be sent to sponsor. That's how you can continue and introduce another prepaid if sponsor is willing to do so down the road.
Hope this helps a little to envision the process.
Regards,
Armand
ArmandV
Re: Event mapping without Elastic Search
Dear customer,
What do you mean by "half blown way " in "Can we have Elastic Search to be implemented half blown way just to address Event Mapping configuration?"
As an alternative be you can use 'Suggestions Search'..
I recommend you have ES installed and configured. not only "half" and please upgrade to at least PeopleTools or 8.60.04 or above since using PT 8.60. (Remark: at least PT 8.59.16 or above when using PT 8.59 )
thank you very much,
Radu,
Oracle GCS
Re: Why would I get Internal Server Error when saving changes to a dashboard
Hi,
Could you please check this knowledge article?
E-Insights: Getting Error "Error: Internal Server Error" When Accessing a Deployed DashboardThanks
Re: Create a XLSX file from a SQR?
Steve - Yes, SQR does not natively supports XLSX file generation as it needs openxml package. Best bet is to use application engine or BI publisher but if you still need an SQR then you can generate the file in CSV and then convert the csv file to XLSX using OS native command.
install csv2xlsx or any utility you would like ⇒pip install csv2xlsx
let $cmd = 'csv2xlsx input.csv output.xlsx'
call system using $cmd # This runs the shell command
-Velu
Re: PeopleSoft IMAGE (PUM) - wget
I had a copy of my pum54 wget script, so i just plugged in the values for pum55 files and they downloaded fine. hopefully they bring back the wget easy-button option, though. super inconvenient when on linux to require downloading from a browser…
Re: Is something up with Doc ID 1641843.2?
Hello johnnollet,
Yes , we found the issue and notified the internal teams. I hope it gets fixed soon