Quality Management on Work Order Completion
Hi, I am setting up the Quality Management module, and there is a requirement to trigger a quality check after the completion of certain operations in the WIP routing process. For this, I have created inspections and specifications. I have configured these specifications on the assembly item with the transaction type set…
-
Work Order Completions to enter time against a work order - Does anyone have a simplified UI entry
We are using Work Order completions to enter time against a work order along with downtime reason codes. I was wondering if anyone has created a simplified user entry screen.
-
Enter Completions inventory detail
Is the Enter Completions page actually functional? I've been trying to use it as I'd like to do multiple completions at once, but I'm getting an error when I have backflush unchecked to fill in inventory details, and if backflush is checked, to fill in starting and ending operations. I cannot find any of those 3 fields…
-
Work Order Completion Issue
Hi Gurus, I'm reaching out to seek assistance with the following issues: I've noticed that for item F101SHM0123 (XS001), there is a detected committed quantity of 1. However, upon searching in "Reallocate item," we couldn't find any transactions associated with this committed quantity. Could anyone please advise on the…
-
Work Order Completion
Does anyone have any idea what the error below is about? nlerror: VALID_LINE_ITEM_REQD You must have at least one valid line item for this transaction. afterSubmit_WC(Ps_lib_WO.js:152) afterSubmitTrans(ps_ue_ApplyTrans.js$15099:185) (ps_ue_ApplyTrans.js$15099:504) This error occurred while I was doing a work order…
-
NSC | Work Order Completion Projected Value changed by -System-
Scenario User wants to know why there was a change in Projected Value of a Work Order Completion made by -System-. Additional information: Costing Method of Assembly Item: Average Costing Method of Component Items: Lot Numbered Solution The first thing to check is the Schedule Inventory Costing preference in the account.…
-
Work order completion with 0 Components
Hello everyone, In our system, it is possible to create a work order completion with only one component having a quantity and the rest being 0. Is there a way to prevent the user from creating Work Order Completion if any components are 0? We use WIP, Work Order Completion With Backflush, and lot items. Thank you, Mahmoud
-
How to Link Work Orders Completion with Work Order in ODBC?
I am trying to get all of the work order completion transactions for a particular work order using the NetSuite data connector. I can get the work order completion transactions with something like "select * from transaction where recordtype = 'workordercompletion';" and I can get the work order transactions with a similar…
-
Work Order Completion > Sublists > Operations
Hello, Is there a way to access the Operations sublist on the Work Order Completion form? When entering a completion, the Completed Quantity field in the operations area is greyed out and records the Completed Quantity entered in the Work Order Completion form's field. Is there a way to add a field Labor Time field to the…
-
Machine resource In saved search
Hello Experts, I am trying to build a Work Order Completion saved search, where I want to bring "Machine Resource" number in the search result. The "Machine Resource" is from Manufacturing Operation task record. Although I am able to bring in the field but result displays no result Can you please help.