Discussions
SuiteWorld brings thousands of innovators, builders, and leaders together to learn, connect, and shape what’s next. This October, explore how to build a stronger foundation for growth through inspiring keynotes, major product reveals, hands-on sessions, and unforgettable moments—all in one place for our biggest event of the year. Join us
NSC | Work Order Completion Projected Value changed by -System-
Scenario
User wants to know why there was a change in Projected Value of a Work Order Completion made by -System-.
Additional information:
- Costing Method of Assembly Item: Average
- Costing Method of Component Items: Lot Numbered
Solution
The first thing to check is the Schedule Inventory Costing preference in the account.
It can be found in Setup > Accounting > Inventory Costing Preferences.
Verify if the costing is running every hour or on a custom schedule.
Refer to SuiteAnswers 65659 for more information about this.
Regarding the GL Impact changed by -System-, this is standard behavior for Lot Numbered Items. When using Lot Numbered Items in transactions which reduce the inventory quantity, it usually uses the average cost first, then system will do a costing recalculation to correct the cost used in the transaction.
Learn how to Refer A Member | Earn the Answer Accepter Badge | Be the Content Creator of the Quarter | Vote for the content you want to see!
