It’s that time of the year again! As we embrace the holiday cheer, we want to share an important announcement regarding our holiday schedule. Our dedicated team of NetSuite Support Gurus will be taking a short break to recharge during the holidays, from December 24, 2024, to January 1, 2025. We’ll be back in full swing, ready to assist you on January 2nd. During the break, feel free to explore the wealth of NetSuite resources on our platform.
As we celebrate the season's joys, we are incredibly grateful for your ongoing support and engagement. Have a fantastic holiday break, and let's gear up for an incredible 2025!
Here are some examples to get your creative juices flowing.
"Did I pay vendor John Doe last month?"
"Take me to my largest sales order for this month."
"What invoices haven't been paid yet?"
NSC | Work Order Completion Projected Value changed by -System-
Scenario
User wants to know why there was a change in Projected Value of a Work Order Completion made by -System-.
Additional information:
- Costing Method of Assembly Item: Average
- Costing Method of Component Items: Lot Numbered
Solution
The first thing to check is the Schedule Inventory Costing preference in the account.
It can be found in Setup > Accounting > Inventory Costing Preferences.
Verify if the costing is running every hour or on a custom schedule.
Refer to SuiteAnswers 65659 for more information about this.
Regarding the GL Impact changed by -System-, this is standard behavior for Lot Numbered Items. When using Lot Numbered Items in transactions which reduce the inventory quantity, it usually uses the average cost first, then system will do a costing recalculation to correct the cost used in the transaction.