Contract Manufacturing Flow – PR and PO Not created through Supply Orchestration from Planning
Summary
Issue is for Fusion Contract Manufacturing process for the Planned Orders released from Oracle fusion Planning Central - Supply Plan.Content
Contract Manufacturing Flow – PR and PO Not created through Supply Orchestration from Planning
Hi Team,
Please see the details below:
Issue is for Fusion Contract Manufacturing process for the Planned Orders released from Oracle fusion Planning Central - Supply Plan.
Steps:
- Contract Manufacturing Org (CM Org) is created.
- Finished Goods (FG) is assigned to CM Org which consists of Service item in its structure.
- BPA exists with Service Item
- All financial setups are completed from Procurement side.
- Supply Plan is created which consists of this CM Org.