Is there a way to make MRP / Planning Workbench consider a Work Calendar?
We would like that the MRP calculations took into account that Holidays and weekends, which would be indicated in a Work Calendar, are not to be considered as part of Item/Vendor Lead times for planning and expected receipt date purchases, meaning, if I need something on Sept 18 2023, and my purchase/vendor lead time is 5 days, I want MRP to ask me to send the PO on Sept 11, so 5 days WITHOUT considering Sept 16 and 17 which are weekends. But MRP, from what I have seen will take Sept 13, so 5 REAL days as the lead time.
Is there a way to use a Calendar to avoid considering these days and also defined holidays like you can do with Work Calendars assigned to Work centers?