Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Resources that alter their resource allocation on a task over time
I have resources that frequently have higher allocated time in the early weeks of a project, then gradually scale down to a "normal" resource allocation level.
For example, the project director might spend 100% of the first week on the project, then 60% of the second week, 40% of the third week, then settle into a rountine with 2 days one week, one day the second week.
To enter this I can enter a task for week one (@100%), week two (@60%), week three (@40%), week four and onwards (@20%), and a task every second week with an additional 20%. A lot of data entry, with a lot of repetitive data.