Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
estimated hours for the project
Actual hours -when entered using Time entry against the task are ADDING to the estimated Hours.Thus % Completion is not correctly calculating.
Is there a reason why actual hours are being added to the original estimated hours?
for example Project has 2 tasks with each task having estimated hour equal to 1 hr
total estimated hours=2
time track and enter new time for one of the tasks as =1 hr
now total estimated hours changes to 3 and making completion %=33.33% instead of 50%
any help is appreciated.