Predecessor relationships
<p>OpenAir supports the same range of dependencies between tasks as Microsoft Project does. This allows the project manager to sequence tasks in a variety of ways:<br/><br/>a). Finish-to-Start (FS). This means the succeeding task cannot start until the predecessor task is finished. OpenAir has always supported this type of predecessor relationship.<br/>b). Start-to-Start (SS). The succeeding task cannot start until the predecessor task starts.<br/>c). Finish-to-Finish (FF). The succeeding task cannot finish until the predecessor task finishes.<br/>d). Start-to-Finish (SF). The succeeding task cannot finish until the predecessor task starts.<br/><br/>The system calculates the start and finish dates of tasks based on the predecessors selected,