Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
New AI Community Guidelines. Please review and follow them to ensure AI use stays safe, accurate, and compliant.
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
NSC | How to create a report will show the difference between Planned Hours and Actual Hours?
Scenario:
A user needs a report that shows the difference between Planned Hours and Actual Hours to track Project, user also wants to have the percentage of the Actual Hour to the Planned Hour. This will allow them track the variance between planned and actual hours which is crucial for evaluating the hours logged in a project record.
User wants to use Planned Utilization by Resource report - which displays the planned time of each resource per Project
Solution:
1.) Navigate to Reports > Time & Billables > Planned Utilization by Resource
2.) Click Customize
3.) Go to Edit Columns and remove the columns:
Utilization
Available Hours
Patrick Fresnosa | Advanced Accounting | SRP | Ask a Guru