Supply Planning Cloud
Discussion List
-
Supply Planning - Price Measure value is not considering price listHi Team, The supply planning price measure is not cosidering the corporate price list values defined for the item. Rather it takes the value form the list price. Please …Raja Sekar 51 views 2 comments 0 points Most recent by Raja Sekar Supply Chain Planning and Collaboration -
How to make component demand by operationsWe have component A and B under in the BOM of FG, the Operations are 50 and 60. Routing set in the 50 OP have 24 hours cycle time. Expect: After run the plan, the deman…Dennis Wang 11 views 1 comment 0 points Most recent by Avinash Erande Supply Chain Planning and Collaboration -
Downtime for a 24 hrs avilable ResourceSummary: We have the requirement to put the scheduled downtime of the resources in the Supply Plan. The resources are 24 hrs available but there would be planned downtim…Nitin.Joshi 21 views 1 comment 0 points Most recent by Thejaswini Kamreddy-Oracle Supply Chain Planning and Collaboration -
Pegging for planned orders created against safety stock demand say not peggedSummary: Why does the pegging for planned orders created against safety stock demand say not pegged in Supply Plan? How can we determine that the planned order was creat…Rahul A 151 views 5 comments 0 points Most recent by Catherine Alequin Supply Chain Planning and Collaboration -
Fusion: PR not created from the planned order where BPA validation fails.PR not created from the planned order where BPA validation fails. Is there a way to bypass this and achieve the requirement? If the BPA is not valid then PR should be cr… -
Any way to link a released planned order to it's associated DemandRequirement : Sales Order and it's associated supply orders should be associated with same serial number. Question : Example: Sales Order demand of Item AB created Plann… -
is there any option for work Order to be consumed by demand in a given time periodSummary: is there any option for work Order to be consumed by demand in a given time period without unfirming the Work orders currently For example, if we have a demand …Priya.George 31 views 6 comments 0 points Most recent by Scott Malcolm-Oracle Supply Chain Planning and Collaboration -
Scheduling Plan run after Successful Completion of Collections RunSummary Trigger Plan run only if Collections completed successfully, else don't run the scheduleContent In EBS/ASCP currently our Client uses a third part software calle…Vinay Srinath 49 views 9 comments 0 points Most recent by Akshay_Jo Supply Chain Planning and Collaboration -
Can Supply Planning Segmentation be pulled into the Segment column in the Supply Plan?Summary: We're currently leveraging Segmentation and Netting rules as a part of our Supply Plan. Is there any way that we can pull the segment an item is tied to in the …Jonathan Ricks 21 views 2 comments 0 points Most recent by Jonathan Ricks Supply Chain Planning and Collaboration -
When does the scheduled for release button turn onSummary: Hello, We would like to know when does the scheduled for release button on the details section of Production Schedule turn on? When we expand the details sectio…SharathBiz 31 views 5 comments 0 points Most recent by M. Bolsinger-Oracle Supply Chain Planning and Collaboration -
Fusion Application - Supply Planning - Work order released from planning Start & completion DateHi Oracle Team, Planned Work order Order released from the planning is not having start date. Please check and provide details, Is there any way from planning we can sen…Raja Sekar 17 views 1 comment 1 point Most recent by Srikanta-Oracle Supply Chain Planning and Collaboration -
Planned Orders Completion dates not collected in Supply Planning from P.S ScheduleSummary: We have collected Planned Orders into Production scheduling and collected these planned orders back to Supply Planning using this new feature where we can inclu…MMA27305 11 views 1 comment 0 points Most recent by Rahul Awasthi-Oracle Supply Chain Planning and Collaboration -
can we use item EFF as a filter on supplies and demands tableSummary: Hello, We have created a Item EFF with value set for ABC classification. We would like to understand if we can bring this as a filter on supplies and demands ta…SharathBiz 21 views 1 comment 0 points Most recent by Sebastian Thomas Supply Chain Planning and Collaboration -
what factors are necessary for each forecasting method.?Summary: what factors are necessary for each forecasting method, where to locate those factors in the system, and then figure out why the system is selecting the forecas…SARTHAK GOSWAMI 11 views 2 comments 0 points Most recent by Gururaman Subramanian-Oracle Supply Chain Planning and Collaboration -
Does Planning collects the returns sales ordersSummary: Does Planning collects the returns sales orders Content (required): Need clarification, if Planning collects the Returns Sales orders. Version (include the vers…Shagaf Hasnain-Oracle 51 views 3 comments 0 points Most recent by KKZ Supply Chain Planning and Collaboration -
Not able to add Labour/Machine resources and overtime shift for a resource in Supply PlanningHi Experts. Hope you all doing good. Just wanted to understand if there is a functionality in Oracle Supply Planning Cloud, using which we can add Labour or Machine reso…SidSaxena 41 views 3 comments 0 points Most recent by Nitin.Joshi Supply Chain Planning and Collaboration -
Can we upload Supplier on hand using custom measure FBDI into Supply chain planning tablesSummary: Hi, Can we upload the Supplier on hand against a custom measure using SCPMeasureImportTemplate? I have created a custom measure which is enabled in 4 dimensions…Vatsala Bharadwaj 31 views 2 comments 0 points Most recent by Vatsala Bharadwaj Supply Chain Planning and Collaboration -
Attribute based Planning - Plan recommending an extra quantity for component itemsPlan type - Constrained, Attribute based Associated the below attribute based netting to the supply plan and, after that plan is suggesting 2 planned orders for supplies… -
How can we pass a free text attribute to planning from Sales OrderOracle Fusion Cloud We have created EFF at sales order line level to be passed to planning for attribute based planning. This attribute is used just to link the demand w…Rithu 31 views 1 comment 0 points Most recent by Prateek_16-Oracle Supply Chain Planning and Collaboration -
Bookings Forecast Number is Capping at 10,000,000 (10 million units)Summary: An analysis of the Booking Forecast generated in the Demand Management module revealed that the generated forecast is being capped at 10 million units per month…Ramesh Choudhary 21 views 1 comment 0 points Most recent by Thejaswini Kamreddy-Oracle Supply Chain Planning and Collaboration -
Attribute Based Planning with ReservationsSummary: We are using attribute based planning to achieve netting based on prespecified rules. The rules are defined as follows – If demand netting attribute is not blan…Durgesh Pandit_ 51 views 4 comments 0 points Most recent by Rithu Supply Chain Planning and Collaboration -
Production Scheduling in mobile/table devicesSummary: Is it possible to access Oracle cloud Production Scheduling application in mobile/table devices?Avinash Erande 11 views 2 comments 0 points Most recent by Avinash Erande Supply Chain Planning and Collaboration -
Data flowing from demand planning (forecast) to supply planningSummary Request to share explanation on data flowing from demand planning (forecast) to supply planning. If any one can provide with white paper it would be very usefulC…User_U6UXL 58 views 5 comments 0 points Most recent by felipe vieira Supply Chain Planning and Collaboration -
Supply Planning - Export Release ErrorsSummary: Supply Planning - Export Release Errors Content (please ensure you mask any confidential information): Hi All, As part of the health check monitoring, we are tr…Venkatesh Periketi 21 views 5 comments 1 point Most recent by Satwik Kumar Patel-Oracle Supply Chain Planning and Collaboration -
How to bring Item EFF values in to supply planningSummary: Business want to see the item EFF value selected from LOV in item masters to be populated in supply planning Buy recommendations planned orders for the visibili…Harikc 81 views 4 comments 0 points Most recent by Venkatesh Periketi Supply Chain Planning and Collaboration -
How is Planned Order Quantity calculated when the item has both "Safety Stock" and "Order Modifier"Plan type : Attribute based constrained Supply Plan Module : Supply Planning Kindly refer below screenshot: Fixed days of supply for the item = 5 Safety stock, Days of C… -
Resource requirement measure to display by item/plan orderSummary: We're trying to create a table where I can show the suggested plan order qty by FG item for a day, and what is the resource requirement hours for that item or p… -
Can I delete a planned order in Supply PlanningSummary: In Supply Plan, Supplies and Demand table, user can manually create a planned order. Is there an option for user to delete/remove a planned order once it's crea… -
Can we get unmerged item column when exporting the build planSummary: we had exported the build plan having multiple items and having multiple measures. In the exported file the items in the column is merged and upon filtering onl…Kaushik V Shankar 31 views 1 comment 0 points Most recent by Prateek_16-Oracle Supply Chain Planning and Collaboration -
Transfer Order consumptionSummary: The requirement is to load and consume all the forecast in the manufacturing plant, and sales will be happening from both manufacturing org and as well as from …Shagaf Hasnain-Oracle 42 views 2 comments 0 points Most recent by Raju Pachigolla Supply Chain Planning and Collaboration