Project Task Import - multiple resource assignees
We are using quite a few features of Netsuite Projects including, projects, Project management, advanced project profitability and several suite apps.
We are using Activities > Scheduling > Project Tasks > Import to import tasks. Each task could have multiple resources assigned.
Our issue: when we import the tasks with multiple resource assignees, it is creating new tasks for every employee assignment, which is not what we want. Has anyone been able to import the tasks and the assignees so that it is in a one to many arrangement?
Should we import the tasks first and then try to do the assignment in a second load?