Discussions
Managing projects with detailed tasks
<p>We currently use MS Project to create projects with a very granular set of tasks. A Some examples are the following - schedule meeting(4 days - 1 hour duration), have meeting (2 hours), install database (4 hours), setup document types (2 hours). A This is needed to get an accurate estimate on the project and give the consultants a detailed task list of what needs to be done. A However, recording time and managing the flow of the actual work during the project becomes next to impossible. A </p><p>An example would be that database setup requires 8 hours instead of