Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Predecessors and Durations
Hi
We need to be able to enter tasks into the system whereby we may for example have 10 days to carry out a task that has 16 hours work. We also need tasks to be able to have predecessors in order that when a plan date moves to the right, all the subsequent tasks also move later.
Does anyone know how can I enter a duration for a task that is longer than the number of hours work? If I input start and end dates to do represent the duration this then overrides the predecessors, so the plan will not change even if the predecessor changes
0