Discussions
Planned Cost not calculated
Dear All
We wanted to get report on Planned cost of each project so as to know and control the cost overrun by periodic review.
To achieve this I have created Job codes, updated cost against each Job codes. The Job code is assigned to user.
When I assign users to a project and update Planned hours, I am expecting to get "Planned Cost" but system won't show the cost.
If Current hourly cost is updated for individual user, then only system responds to it and calculates Planned Cost.
Logically system should recognize the cost maintained in Job code as relationship between User ->Job code -> Cost is already established. I don't want to update current hourly cost for 1000 users where as prefer to update 35 Job codes with cost which is feasible to update and maintain on Cost revision.