Divide assigned hours evenly among assignment group members
<p>Per July 2009 release:</p><p>Previously, for accounts that leveraged the feature a€œInput planned hours for each user assigned to a taska€, the assigned hours entered on a task were multiplied by each member of the assignment group. For example, if there were 5 members of an assignment group that was assigned to the task and the assigned hours were 100, the total number of planned hours of the task would be 500, with each member assigned to 100 hours.</p><p>A a€˜Divide hoursa€™ option has now been added for each task assignment row. With this new feature, users have the option to divide