We are currently not using the PO module within NS, but I am using our Sandbox account to try to figure out if it is something we could use, so my question may be self explanatory or I'm missing something.
When I enter a PO for 10,000 items @ $1 and I receive 8,500 of those items, why does NetSuite allow me to bill and pay for all 10,000 of those items ($10,000 versus the $8,500 that I actually owe)? Is there something that would prevent me from paying for something that I did not receive? Isn't this the point of performing the 3-way match between PO, receipt and bill?
In this case, let's say I override the bill amount and enter in $8,500 (which I would have to go back and look at what was receive and manually calculate from what I can tell) and then I subsequently receive the remaining 1,500 items. If I had receive and paid for the original PO, can I enter in this receipt/bill against the original PO?
Any help understanding the workflow of this module would be helpful.
Thanks!
-Carrie