Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Update your Profile with your Support type to get your Support Type badge.
Expand your NetSuite knowledge by joining our Ask A Guru Live sessions. RSVP on this event now.
Uncover the power of data with the Analytics Hub —your ultimate guide to mastering NetSuite Saved Searches and Reports. Simplify the complex and unlock your organization's true potential. Dive into the Analytics Hub now and soar to new heights!
To help you get the most out of your 2025.2 Release Preview account, review the topics outlined in the 2025.2 Release Preview Guide.
Share Your SuiteWorld Experience & Earn a Special Badge!
Intelligent Payment Automation version 1.0.3 is now available in the SuiteApp Marketplace. The SuiteApp, powered by BILL, lets you automate payments, manage vendor details, and bank account information within NetSuite. Learn more
Manually Set Project Task Due Date
Howdy! We're working with Project Tasks to plan out our project work. NetSuite's default behavior seems to require (1) Allocation %, (2) Estimated Hours of Effort, and (3) the Employee's Work calendar (ie: hrs per day available to work). With these inputs the system arrives at a calculated Due Date.
This doesn't work well in a lot of cases. We have scenarios in which:
* The End Date is fixed; it must be done by this date
* The task may only require 10 hours of work, but will be spread inconsistently over 5 weeks
* There may be multiple people Assigned to work on a Project Task, each with varying levels of effort.
0