  • Hi, I do not recommend use of Analytics for this task. Advanced BoM structure is too complex to be handled by generic Analytics tool. There can be multiple revisions for every BoM, there can be different default BoMs for Assemblies for different locations, Every sub-assembly can have different validity for different…
  • Hi, This is not bug, but intentional behaviour, to prevent transactions inconsistency. Once related WO is created and Outsourced PO line is closed, related Work Order is closed as well. Since the Closed Work Order can NOT be reopened, therefore system don't allow to reopen related Outsourced Purchase Order Line. The way…
  • Hi, Probably easiest solution is to add custom field - checkbox on Work Order and whenever someone modify component list, they should check the checkbox. It should be possible to automate this process through suite script to compare component list with the BoM revision attached to WO and if they differ checkbox will be…