Hi Alex, Thank you for your assistance, The job manager field is available on the workflow and we incorporated below formula into the workflow Condition: Project : Job Manager Is Not Empty And Project : Job Manager = Current User When we are creating a test expense report and trying to approve the same from user's login…
-
Hello @Patrick Fresnosa-Oracle, Thank you for your detailed response and insights. Unfortunately, we cannot proceed with the solutions you suggested for the following reasons: 1️⃣ Suggestion 1 – Labor Cost at Task Level: While setting labor costs at the task level is a valid approach, we are currently managing over 200…
-
You can try with vendor bills and Journal entries, it should work. But, Yes - most of the functionality around projects based on Employee timesheets and expenses
-
Hey Vernita, The Committed Cost comes from employee timesheets that are not yet approved. However, based on my observation, the Committed Cost column may not work correctly if the Job Costing and Project Budgeting feature is enabled in your account. If this feature is currently turned on, you can try disabling it,…
-
You can give planned work at task level so that it will auto set end date. Example: I have given planned work as 18000 hours which automatically set end date as 8/17/2033 and save, then you can edit the same task and enter budget on monthly basis
-
System allowing us to do budgeting at task level for next 10 years (120 Months)