Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Update your Profile with your Support type to get your Support Type badge.
Uncover the power of data with the Analytics Hub —your ultimate guide to mastering NetSuite Saved Searches and Reports. Simplify the complex and unlock your organization's true potential. Dive into the Analytics Hub now and soar to new heights!
To help you get the most out of your 2025.2 Release Preview account, review the topics outlined in the 2025.2 Release Preview Guide.
Nominate Your Peers for NetSuite Support Community's Choice of the Quarter! Submit your nomination today.
Intelligent Payment Automation version 1.0.3 is now available in the SuiteApp Marketplace. The SuiteApp, powered by BILL, lets you automate payments, manage vendor details, and bank account information within NetSuite. Learn more
Tracking projects without time entries (statuses/overwrite actual time)
Is this possible with Project Management in standard to track projects and change % completion without entering actual time in the system against the project? (or overwrite actual work for each task)
My aim is to get percent work complete % according to task statuses and still assign generic resources to the tasks for planning purposes.
Help Center says that when the status of all tasks is Completed, percentage work complete % should show 100% and the same for individual tasks: when the task status is Completed, the percentage is 100%.
https://5033030-sb1.app.netsuite.com/app/help/helpcenter.nl?fid=section_3740077129.html
So I expect Percent work complete to be 100% in the screenshot below:
2