Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
New AI Community Guidelines. Please review and follow them to ensure AI use stays safe, accurate, and compliant.
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
How to get Reschedule in messages to help identify items that need to be expeditied
We are using MRP Demand Planning and having trouble getting the RESCHEDULE IN Action Messages.
System is driving the right planned purchase orders for the right quantities but the due dates for the PO's is based on the item lead time. We are hoping to use the RESCHEDULE IN Action messages to identify which existing PO's need to be rescheduled in to satisfy the demand plan.
We have tried setting the RESCHEDULE DAYS value from 0 to 90
We have tried setting the RESCHEDULE HORIZON value as blank, 30, 60, 90, and 180 days
Looking for any advice regarding what is critical to set up for the RESCHEDULE DAYS Action messages to work