Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
New AI Community Guidelines. Please review and follow them to ensure AI use stays safe, accurate, and compliant.
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Adjust Work Order Planned Start Date
Hi There
There is a scenario as follows:
There is a released work order for 100 qty of a good.
20 qty is produced and completed using a work order completion.
The remaining 80 qty will be produced at a future date at the request of the customer.
WIP and routing is in use as well as the manufacturing task scheduler.
How can the planned start date of the work order be pushed out into the future?
Is this something that can be modified with a script?
thanks