Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
New AI Community Guidelines. Please review and follow them to ensure AI use stays safe, accurate, and compliant.
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Manufacturing Routing Connection Type > Work Order Completion
Hello Team,
In our Manufacturing Routing setup, Operations are linked with a Finish-to-Start connection. My understanding is that Operation 10 must be fully completed before Operation 20 can begin.
I created a Work Order Completion for 7 out of 10 quantity in Operation 10.
However, after that, I was still able to create a Work Order Completion for 10 quantity in Operation 20.
Could you please clarify why the system allowed Operation 20 to be completed with 10 quantity when only 7 quantity was completed in Operation 10?
Kindly advise. Thank you.
0