Manufacturing Routing Connection Type > Work Order Completion
Hello Team,
In our Manufacturing Routing setup, Operations are linked with a Finish-to-Start connection. My understanding is that Operation 10 must be fully completed before Operation 20 can begin.
I created a Work Order Completion for 7 out of 10 quantity in Operation 10.
However, after that, I was still able to create a Work Order Completion for 10 quantity in Operation 20.
Could you please clarify why the system allowed Operation 20 to be completed with 10 quantity when only 7 quantity was completed in Operation 10?
Kindly advise. Thank you.