Resources that alter their resource allocation on a task over time
I have resources that frequently have higher allocated time in the early weeks of a project, then gradually scale down to a "normal" resource allocation level.
For example, the project director might spend 100% of the first week on the project, then 60% of the second week, 40% of the third week, then settle into a rountine with 2 days one week, one day the second week.
To enter this I can enter a task for week one (@100%), week two (@60%), week three (@40%), week four and onwards (@20%), and a task every second week with an additional 20%. A lot of data entry, with a lot of repetitive data.