Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
New AI Community Guidelines. Please review and follow them to ensure AI use stays safe, accurate, and compliant.
Keep an eye out for upcoming NetSuite events, including meetups, workshops, and webinars. These sessions are a great way to connect with peers, learn from experts, and stay current on the latest NetSuite updates and best practices. Registration links are provided in each event.
SuiteWorld | October 25–28, 2026 | Las Vegas Where our community gets ready for what’s next!
SuiteWorld brings thousands of innovators, builders, and leaders together to learn, connect, and shape what’s next. This October, explore how to build a stronger foundation for growth through inspiring keynotes, major product reveals, hands-on sessions, and unforgettable moments—all in one place for our biggest event of the year. Join us
SuiteWorld brings thousands of innovators, builders, and leaders together to learn, connect, and shape what’s next. This October, explore how to build a stronger foundation for growth through inspiring keynotes, major product reveals, hands-on sessions, and unforgettable moments—all in one place for our biggest event of the year. Join us
Using Resource Allocations to drive Project Timelines
Good morning!
We've been using ASSIGNMENTS for the past couple years on projects. The benefit being that Assigned Hours on a Project Task appear to be the only way to let NetSuite derive estimated/calculated End Dates.
Ex: Resource with a 40hr/wk work calendar, assigned 80 hours of work on a task, at 50%. NetSuite will calculate 4-weeks to do that work. Assuming a Start Date of 2/1/2021, NetSuite would project the end date at 2/26/2021. Importantly, the Project Task dates get updated with this information, as does the overall Project end date.
The two big drawbacks we have with ASSIGNMENTS are:
- If a user starts the work for 2 weeks, gets pulled onto another priority for 2 weeks, then comes back to finish the work: Planned time ended on the 26th, but there's really 2 weeks of hours left to be completed. Planned Utilization reports and Project Charges Forecasts are off with regard to the dates.