Discussions
Check out Oracle NetSuite upcoming events and conferences here
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Update your Profile with your Support type to get your Support Type badge.
Expand your NetSuite knowledge by joining our Ask A Guru Live sessions. RSVP on this event now.
Get ready to take on exciting new challenges and become the next SuiteMaster of the Month!
Join the largest gathering of the NetSuite Community at SuiteWorld in Las Vegas, September 9-12! Discover cutting-edge innovations, attend insightful sessions, network with industry leaders, and elevate your business to new heights. Register here!
Work Calendar Limitations
We are currently implementing SuitePeople, and have run into an issue with the work calendars. First some background:
- Employees normally work Monday-Friday
- Occasionally employees will be required to work over the weekend.
- We schedule our project in NetSuite using project tasks, and project task assignments
The issue we ran into a few years ago was that if an employee's work calendar was set to M-F, and they were to be assigned to a project task that was scheduled on the weekend, the assignment would fail with the following message:
At least one employee assigned to the task Weekend Work has no working hours between the start date 8/14/2021 and end date 8/15/2021.