Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Please note that on Friday, March 20, 2026, at 8:00 PM Pacific time, our Case Management System will undergo a scheduled maintenance for approximately 4 hours. During this time, case creation via SuiteAnswers will be unavailable and inbound calls will be routed to Customer Service.
How are Remaining Work and Calculated Work computed in a project?
I am looking at the project where it's showing these numbers:
Calculated Work = 335
Planned Work = 304
Allocated Work = 330
Actual Work = 309
Remaining Work = 26
See screenshots:
Question: Can someone clarify how did the Remaining Work and Calculated Work come to be? As per reading SuiteAnswers and testing, the Remaining Work should be Estimated Work - Actual Work, but in this case, the math doesn't make sense.
Thanks and regards,
Lea Columna