Discussions
Check out Oracle NetSuite upcoming events and conferences here
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Update your Profile with your Support type to get your Support Type badge.
Expand your NetSuite knowledge by joining our Ask A Guru Live sessions. RSVP on this event now.
Get ready to take on exciting new challenges and become the next SuiteMaster of the Month!
Unleash the Power of AI with NetSuite's Intelligent Recommendations
Don't miss out on the opportunity to boost sales and customer satisfaction. Elevate your business with NetSuite's Intelligent Recommendations.
Don't miss out on the opportunity to boost sales and customer satisfaction. Elevate your business with NetSuite's Intelligent Recommendations.
How are Remaining Work and Calculated Work computed in a project?
I am looking at the project where it's showing these numbers:
Calculated Work = 335
Planned Work = 304
Allocated Work = 330
Actual Work = 309
Remaining Work = 26
See screenshots:
Question: Can someone clarify how did the Remaining Work and Calculated Work come to be? As per reading SuiteAnswers and testing, the Remaining Work should be Estimated Work - Actual Work, but in this case, the math doesn't make sense.