Hi There
I have enabled the 3 way vendor bill match for testing without any adjustments to the workflow.
There has been one vendor quantity difference value set up
The resulting bill was auto approved.
1 Is the quantity discrepancy on the vendor record (1 in this example) suggesting that any quantity that is billed over and above the purchase order original ordered quantity will be flagged for approval routing? e.g. if a quantity of 6 was billed when the original PO had quantity of 5
2 Is there a way to route vendor bills for approval if the quantity billed is greater than the quantity received?
Edit: I found the answer to that: by adjusting the Item Receipt Quantity Difference on the Vendor record.
3. Do the tolerance and quantity difference levels need to be set on each vendor record? Can they be set at a company wide level? (with any differences to the blanket company wide level being set on the individual vendor records)? .e.g A company wide rule is set that any quantity difference of 2 will result in the approval routing being triggered. Though for one particular vendor, the approval routing will only be triggered if the quantity variance exceeds 5
4 (additional question): For a vendor with this limit:
Why would a bill with quantity billed of 16, where the original PO quantity was 15, be pending approval with the exceptions:
Bill quantity exceeds PO quantityBill amount exceeds PO amount
Isn't the difference of 1 extra quantity billed within the limit of 5? Or have I misinterpreted the 'Vendor Bill Purchase Order Quantity Difference' field's purpose?
I also tested with a change from vendor bill-purchase order difference to vendor bill-purchase order quantity tolerance:
The workflow history notes after the change. This is was also routed for approval despite the quantity billed being 16, the PO quantity being 15:
Thanks