We are seeing planned PO's being generated in the workbench for earlier dates than PO dates for items that already have actual PO's.
We need the actual PO to be prompted to be brought in to an earlier date, before the system tells us to create a new PO at an earlier date, and cancelling the existing PO.
The problem is the system prioritizes placing a new planned order over rescheduling the PO. I need the PO to be rescheduled first, and then if the actual PO's are not enough to cover the demand, then I want planned PO's suggested
Example is,
:
38-9105 - Instead of creating Planned PO 27458064 to arrive 5/31 and Rescheduling Out PO12250 from 5/28 to 6/7, I want PO 12250 to stay where it is, or moved to 5/31 if it has to be, but then plan the Planned PO 5/31 or later?