Discussions

Check out Oracle NetSuite upcoming events and conferences here
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Update your Profile with your Support type to get your Support Type badge.
Don't miss out on our Weekly Quiz! You only have until May 30, 2PM EST to comment your answers and earn rewards! Click here for more details.
Expand your NetSuite knowledge by joining our Ask A Guru Live sessions. RSVP on this event now.
Community Poll: What sort of content would you like to see more of?

MRP not Rescheduling purchase orders correctly

edited Jan 19, 2024 8:40PM in Ask A Guru 1 comment

We are seeing planned PO's being generated in the workbench for earlier dates than PO dates for items that already have actual PO's.

We need the actual PO to be prompted to be brought in to an earlier date, before the system tells us to create a new PO at an earlier date, and cancelling the existing PO.

The problem is the system prioritizes placing a new planned order over rescheduling the PO. I need the PO to be rescheduled first, and then if the actual PO's are not enough to cover the demand, then I want planned PO's suggested

Tagged:

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!

Leaderboard

Community Whiz

Quarter 2 ((Apr-Jun 2024) )

This Week's Leaders

This Month's Leaders

All Time Leaders