Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
New AI Community Guidelines. Please review and follow them to ensure AI use stays safe, accurate, and compliant.
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
How to Handle Construction Retention for Milestone Billing(Tax on Net Amount+Retention Release)
I’m working on a milestone-based billing setup where each milestone has a retention amount held by the customer. I would like to clarify the correct way to handle this scenario in NetSuite.
Business Case:
- Milestone Billing With Retention Deduction
- Example: Certified milestone value = RM1,000,000
- Retention 10% = RM100,000
- Tax should be applied only on the net amount (RM900,000), not on the retention.
- Each milestone invoice must show the gross milestone value, retention deducted, and tax calculated on the net.
- Retention Release at Final Milestone
- When the project is completed, the retention amount (RM100,000) will be released.
- At that point, tax must be applied on the retained amount