How are Remaining Work and Calculated Work computed in a project?
I am looking at the project where it's showing these numbers:
Calculated Work = 335
Planned Work = 304
Allocated Work = 330
Actual Work = 309
Remaining Work = 26
See screenshots:
Question: Can someone clarify how did the Remaining Work and Calculated Work come to be? As per reading SuiteAnswers and testing, the Remaining Work should be Estimated Work - Actual Work, but in this case, the math doesn't make sense.
Thanks and regards,
Lea Columna