Trace in EPCMCS
Summary:
Trace allocation map for multistep
Content (required):
When I try to create a multistep trace allocation map, It gives the total for the starting point in each step.
For example: If it is a 3-step map Product-Activity-Account, it gives details of each activity cost for the product (which is ok) but then gives the total cost from each account for the product (this is also ok). But If I select an Activity then it shows which accounts it is related to but the costs shown are the total costs for all the activities for the product.
What I was expecting, when I select an activity then the links should be only to those accounts related to that activity and the cost for the accounts should be related to the selected activity only (and not the total for that product from all the activities).