Budgetary Controls are not working as per the expectations
Summary:
When the cost exceeds the budgeted amount for a specific project, it should trigger an error stating that "funds are not available/Insufficient funds". We verified the below setups
Manage Financial Plan types- At project level, the control is "Absolute".
Manage Budgetary Control - It is set to "yes" at Ledger, BU and BU functional level.
Despite of these setups, budget control is not working. Any suggestions/ideas from anyone would be greatly help us in sorting the issue. Thanks in Advance.
Regards,
Sai Chandana
0