Is there a way to restrict planned order release from the supply plan?
We have a requirement where we need to consider the storage capacity of our storage facility before confirming Purchase Requisitions.
Our approach is as below.
- Create 2 supply plans
- Load external forecast to supply plan1 and generate planned orders. All planned orders of supply plan1 are not released.
- Get storage capacity information from storage facility
- Export planned orders from supply plan1 and use them to create forecast file as mentioned in below step-5
- Create a new forecast file with only the items that'd be stored in this particular storage facility - this forecast will contain adjusted planned order quantities and dates ( exported in step-4)
0