Hello,

We are using 5 days ON 2 days OFF calendar and the resource availability calculation is working if 24x7 availability is set to yes. However, for 24x7 flag set to No, the resource availability loaded through FBDI file is not reflecting properly. Resource availability is being split into weekends (sunday) and it is not expected. Could anyone please help to find the root cause for this issue.?

Content (required):


Version (include the version you are using, if applicable):

Oracle Supply Planning 21D