Commitments Cost not picked up by system, why?
Hello,
I created an invoice for a project and saved it, now whenever I run 'Import Commitments' process followed by 'Update Project Performance Data' process, the cost is not imported in the system. Attached image of 'Review Project Performance' for that project where I can see Actual cost but Commitment cost is 0.00.
Attached 2nd image of Project Unit Setup where the checkbox of 'Other commitments' is checked.
Am I missing something, please let me know.
Thanks and Regards.
0