Summary

Need inputs on results of S&OP Plan

Content

I need to clarify results based on the analysis of a simple S&OP Plan. Here are the observations:

1. Does Sales Order demand  drops as the actual date moves past SO due date?

2. Are only Released Work Orders considered for Supply Plan calculations?

3. While Planned Orders are loaded / visible in Plan Inputs they are not considered for Supply Plan calculations?

4. System generates production plan based on demand and supply , however if it encounters a work order for a given combination/time bucket , it does not suggest a plan on top of it and tries to build this a month ahead.