We are trying to understand why a planned order is suggested for an item in the following case
- On hand 18
- Safety stock not planned
- Forecast all the long, about 1 EA per week
- PTF : 5 days, DTF : 20 days
- The replenishement is a buy type, with an overall lead time of 13 days.
From Material Plan, we can see that the item will be short in about 6 months (January 2024) if we do not replenish.
However, we have a planned order suggested in about a month (for a due date on half September 2023) pegged for half of it to the forecasts that begin in January 2024. Quantity is this beacause we have a multiplier.