Summary: Client is MTO and MTS global manufacturing company. We are implementing SCM cloud to bring the most enhanced capability and supply planning in the company using he SCM cloud supply planning functionality.
One of the key features we are using is the Gantt chart or graph for our rough cut capacity planning (RCCP)and master production planning (MPS).
Our requirement is as below and we are unable to configure the system:
1. We have in each MFG plant: assembly lines with list of resource.
a. We need to generate a capacity load view that will give us top level single view of